Project management planning

Estimate at Completion (EAC) [Output/Input]. The expected total cost of a schedule activity , a work breakdown structure component , or the project when the defined scope of work will be completed. EAC is equal to the actual cost (AC) plus the estimate to complete (ETC) for all of the remaining work. EAC = AC plus ETC. The EAC may be calculated based on performance to date or estimated by the project team based on other factors, in which case it is often referred to as the latest revised estimate. See also earned value technique and estimate to complete .

Project management planning

project management planning

Media:

project management planningproject management planningproject management planningproject management planning